Project Dashboard

PDF

This tutorial illustrates the Project Dashboard.


 

Which information does the Project Dashboard provide?


The Dashboard of the project is the initial page of Sablono. Here you can find general counts of your project. For example, on the very top of the page you see an activity count for your project. It is presented as a progress bar in which activities that are already done are shown in green.

Right below you see information about critical deliverables (right to left):

  • Count of deliverables which don’t have a start or due date assigned yet.
  • Count of deliverables which are behind schedule (that means not started before start or endet before due date).
  • Count of deliverables which have open obstructions.
  • Count of deliverables which have open issues.
  • Count of deliverables which have infos assigned.

If you click on one of these cards you will be forwarded to a list of those deliverables. In this list you can dive into more detail reviewing the state on each activity assigned to the deliverable or notes reported, to understand what these numbers really mean for the delivery of your project.

Below these cards, you will find a Progress Curve by Deliverable State. The yellow line in the chart shows how many deliverable should have reach the state you selected from the dropdown above at each point in time (x-axes). The blue line shows how many actually have reached that state at each point in time. That means, you and your team are working before schedule as long as the blue line is above the yellow one. Please note, that you have to create a process template and assign it to your deliverables before the chart will be shown.

On the right hand side you can see information on the latest Inspections that took place. You can click on a specific inspection to see details about it on the Inspection Timeline.

If you continue scrolling down the page, you will find a planned vs. actual by deliverable type bar chart. Please select a process template from the dropdown list. Afterwards the bar chart will show you how many deliverables were planned to have reached a certain state by now and how many really did.

 

Gain an a quick, yet accurate understanding of your project by simply navigating through your project’s Dashboard in Sablono.